Daily The Business

Omar Ayub urged to resolve dispute between SPEC Energy and PPL

Our Special Correspondent

LAHORE: The energy sector industry circles have urged the Federal
Minister for Power and Petroleum Division Omar Ayub Khan to resolve
the ongoing controversy between SPEC Energy DMCC and Pakistan
Petroleum Limited with regard to setting up of a gas process facility
(GPF-III) at Gambat, Sindh in order to ensure the availability of gas
before coming winter.

The industry circles believe that the remaining span of four months
before the start of winter the season is crucial to complete the
project and the federal minister should ensure completion of the
project without delay.

The project is an LPG recovery project being awarded to SPEC in 2016.
Almost 80 per cent of the project has been completed. However, both
the sides have entered in successive litigation that has caused undue
delay in completion of the remaining 20 per cent work on the project.

The energy sector circles are of the view that availability of 50MMCFD
gas with the completion of the project would be highly useful for the
industry in case the project is completed before the coming winter.
This induction of 50MMCFD gas would make many industries operative in
the country, they added.

They have urged upon the PPL to sit down with the contractor and
resolve it amicably, especially when SPEC Energy is ready to settle
down the disputed scope of work and completed remaining work as early
as possible. These circles have stressed the point that excessive
litigation would result in a loss of national exchequer at the end of
the day and the project can be operational in five to six months
subject to the readiness of both sides to sit down and resolve it
amicably.

The contract was a turnkey project where SPEC was responsible for all
the completion of the works on the project against the price of the
contract, which payments were to be made on the completion of work
done by SPEC in line with the terms and conditions of the Contract. In
order to ensure the timely completion of the Project, SPEC Energy
started off with the work and performed ahead of schedule in the
finalizing of initial drawings and designs, and for the
procurement/preparation of various equipments in advance had even
taken a loan for this purpose.

Matt Yeknian, a representative of SPEC Energy said all the works done
by SPEC in line with the contract, and in accordance with the norms of
an EPC contract were rejected, objected, delayed and repelled by PPL.
This led to the performance of additional works being performed by
SPEC which was beyond the contract, which resulted in the increase in
price of the contract and also the extension of the contract.

However, all goodwill gestures on both sides are proving a futile
exercise and both sides are stuck up despite their intention to
resolve it amicably. Therefore, the industry circles have urged the
Federal Minister for Power and Petroleum Division to play its part in
bringing an end to the dispute in the larger interest of the national
economy.

Despite repeated attempts, no one from PPL was available to comment.
Head of Corporate Communications Saqib Anis was also not available to
comment on the dispute.

Leave A Reply

Your email address will not be published.

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. AcceptRead More

Privacy & Cookies Policy